How to Change an operator during a cycle time ?
Posted: Thursday 12 July, 2018 - 07:59
Hey All,
I am new here in this forum.
Now I have this challenge, can somebody give me hint how to solve this:
I am creating a modell of assembly operations, in which cycle times of individual servers (=worksteps) can last 16 hours, for example. The operators are working in 2 shifts (8 hours/shift), in order to minimize the needed total time for the worksteps.
How we can change from a morning shift to a evening shift, when the task has not been finished ?
Can I call operators from 2 separated teams, which have their own availability times, perhaps ?
Best Regards,
Jarkko, Finland
I am new here in this forum.
Now I have this challenge, can somebody give me hint how to solve this:
I am creating a modell of assembly operations, in which cycle times of individual servers (=worksteps) can last 16 hours, for example. The operators are working in 2 shifts (8 hours/shift), in order to minimize the needed total time for the worksteps.
How we can change from a morning shift to a evening shift, when the task has not been finished ?
Can I call operators from 2 separated teams, which have their own availability times, perhaps ?
Best Regards,
Jarkko, Finland