Sequence Problem
Posted: Friday 13 March, 2015 - 15:03
Hi Incontrol Community,
i need to solve one Problem with Simulation. For that reason i use Enterprise Dynamics.
Initial data:
I have 3 Products(ressource):
TB - 1
BL - 1
ML- 1
the logic for the sequence: Event(E1) needs 2 days (cycletime) of Product TB (amount of 1) to generate one Endproduct.
"and" stands for random processes, the constraint is that there is only one Product which is avaliable
Sequence (see attached file for better understanding):
E1 (2days) TB(1)->E2 (3days) TB (1) and E3 2(days) TB (1)->E4 (3 days) BL (1) and E5 (2days) BL (1)-> E6 (2days) ML (1) and E7 (2 days) ML(1)
Problems:
1. First of all i need to set label on the atoms(Products) so i can distinguish between each ressource. After that i need to do an Input strategy according to attached file.
2. Second stept is to set different Events and to define the cycletime according to the data in attached file, for example Event 1 need 2 days to generate one Endproduct, for that reason i take "Server" atom.
3. Is there any possability to use monte-carlo simulation to compare different results? Atom which can be used to compare rusults is the "Gantt"atom i think.
I would realy appreciate if you can adjust my model or simplify it somehow.
Best regards
Dawr
i need to solve one Problem with Simulation. For that reason i use Enterprise Dynamics.
Initial data:
I have 3 Products(ressource):
TB - 1
BL - 1
ML- 1
the logic for the sequence: Event(E1) needs 2 days (cycletime) of Product TB (amount of 1) to generate one Endproduct.
"and" stands for random processes, the constraint is that there is only one Product which is avaliable
Sequence (see attached file for better understanding):
E1 (2days) TB(1)->E2 (3days) TB (1) and E3 2(days) TB (1)->E4 (3 days) BL (1) and E5 (2days) BL (1)-> E6 (2days) ML (1) and E7 (2 days) ML(1)
Problems:
1. First of all i need to set label on the atoms(Products) so i can distinguish between each ressource. After that i need to do an Input strategy according to attached file.
2. Second stept is to set different Events and to define the cycletime according to the data in attached file, for example Event 1 need 2 days to generate one Endproduct, for that reason i take "Server" atom.
3. Is there any possability to use monte-carlo simulation to compare different results? Atom which can be used to compare rusults is the "Gantt"atom i think.
I would realy appreciate if you can adjust my model or simplify it somehow.
Best regards
Dawr