Hello,
In my model i need to use some transporters to transport products.
The transporters are working 5 hours.
The transporters needs a interruption (pause) of 30 minutes after 2 hours working, how can i do this?
HR interrupting
Re: HR interrupting
Hi svendevries,
The Availability Control atom allows you to control the availability of other atoms. If an atom is set to unavailable it will stop executing the tasks for which that atom was designed. Connect the Mtbf Mttr Availability atom to the input channel of the Availability Control atom and set the Mtbf to hr(2) and the Mttr to mins(30).
Regards, Nick
The Availability Control atom allows you to control the availability of other atoms. If an atom is set to unavailable it will stop executing the tasks for which that atom was designed. Connect the Mtbf Mttr Availability atom to the input channel of the Availability Control atom and set the Mtbf to hr(2) and the Mttr to mins(30).